Solar Approval & Installation Process

Here's what you can expect for the end-to-end Solar Installation process. We'll be with you every step of the way to make this process as seamless as possible.

1

Quote

Homeowner Basic Information - Utility Bill, Name, E-mail, ID, Title, Credit. Initial design proposal. Best rates guaranteed.
2

Contract

Site survey photos. Finalize scope of work and payment method. Signed contracts.
3

Design Package

Custom built system meeting code and engineering requirements approved by homeowner.
1-3 weeks
4

Interconnection and Permitting

Secure applicable rebates. Utility company & local requirements met.
2-4 weeks subject to change pending utility & local requirements
5

Installation

Equipment procurement. Schedule installation date. Installation.
2-3 week lead time pending equipment availability.
1-2 day installation, subject to local requirements
6

Inspection

Local electrical & building inspections - pass guarantee.
1-3 weeks, pending local requirements & availability of inspectors
7

Activation

Utility Permission to Operate. Extended Warranties. System Monitoring.
2-4 weeks, pending utility availability